Yorkon and Tesco Set New Record for Speed of Construction
Record
breaking site construction
video produced by us for
Yorkon and Tesco
Golden
Media produce films for
Yorkon, Portakabin and Tesco.
Mike
Sherwood of Yorkon says:
"I
would like to thank you on behalf
of Yorkon and Tesco, you have
done a great job on the video
and at short notice, both Yorkon
and the people at Tesco are
highly delighted with the end
result".
The entire building was manufactured less than a week after the
instruction was received from Tesco. Working through the night and over
a weekend, Yorkon then delivered and installed 26 modules in an
accelerated programme of one unit every 30 minutes, achieving a
watertight envelope as fast as possible, ready for the shop fitting
teams to move in.
The interim Tesco store is helping to ease some of the problems
facing the flood-hit community of Workington. It was open and trading
just 13 days after start on site.